Mathematics, 09.09.2020 16:01, tiffanybrown703

There is a machine shop with only one machine. Arrival rate to the shop is 10 parts per hour on average. The average machining time is 5 minutes per part. The machine shop is considering replacing the old machine with a new high speed machine, which is expected to reduce machining time by 20% (4 minutes per part). Also, the shop is expecting attracting 20% more customers (12 parts per hour), with the new machine. Compare the expected time in the shop for each part with the old and with the new machine. How much % can we reduce the time in the shop by introducing the new machine?

answer
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 20:30, derick263
The areas of two similar triangles are 72dm2 and 50dm2. the sum of their perimeters is 226dm. what is the perimeter of each of these triangles?
Answers: 1
image
Mathematics, 21.06.2019 22:00, tyheath42
Jayne is studying urban planning and finds that her town is decreasing in population by 3% each year. the population of her town is changing by a constant rate. true or false?
Answers: 1
image
Mathematics, 21.06.2019 23:30, meiyrarodriguez
Write an inequality for this sentence the quotient of a number and -5 increased by 4 is at most 8
Answers: 1
image
Mathematics, 22.06.2019 05:00, cheerkennedym2594
Which number is composite a.9 b.5 c.11 d.2
Answers: 2
Do you know the correct answer?
There is a machine shop with only one machine. Arrival rate to the shop is 10 parts per hour on aver...

Questions in other subjects:

Konu
Mathematics, 12.02.2021 09:30
Konu
Mathematics, 12.02.2021 09:30
Konu
Chemistry, 12.02.2021 09:30