Minutes per unit Workstation HiFi-1 HiFi-2
1 6 4
2 5 5
3 4 6
The daily maintenance for stations 1, 2, and 3 consumes 10%, 14%, and 12%, respectively,
of the maximum 480 minutes available for each station each day. Determine the optimal
product mix that will minimize the idle (or unused) times in the three workstations.

answer
Answers: 2

Other questions on the subject: Engineering

image
Engineering, 03.07.2019 14:10, kayabwaller4589
When at a point two solid phase changes to one solid phase on cooling then it is known as a) eutectoid point b) eutectic point c) peritectic point d) peritectoid point
Answers: 3
image
Engineering, 04.07.2019 18:10, DestyHilBan1183
Adouble-strand no. 60 roller chain is used to transmit power between a 13-tooth driving sprocket rotating at 300 rev/min and a 52-tooth driven sprocket. a) what is the allowable horsepower of this drive? b) estimate the center-to-center distance if the chain length is 82 pitches. c) estimate the torque and bending force on the driving shaft by the chain if the actual horsepower transmitted is 30 percent less than the corrected (allowable) power.
Answers: 3
image
Engineering, 04.07.2019 18:10, Talos02
Burgers vector is generally parallel to the dislocation line. a)-true b)-false
Answers: 2
image
Engineering, 04.07.2019 18:10, tobyhollingsworth178
Which from the following instrument is commonly used to detect the high pitch butzing sound in bearings? [clo4] a)-digital ultrasonic meter b)-infrared camera c)-spectroscopic d)-vibrometer
Answers: 2
Do you know the correct answer?
Minutes per unit Workstation HiFi-1 HiFi-2
1 6 4
2 5 5
3 4 6
The daily maintena...

Questions in other subjects:

Konu
English, 10.01.2021 14:00