Business
Business, 13.03.2020 18:34, indiareed0orv5ul

Assume that activity G has the following times: Early start time 7 days Early finish time 13 days Late start time 15 days Late finish time- 21 days Which of the following statements is TRUE about activity G?a. Activity G takes 14 days to complete. b. Activity G has a slack time of 8 days. c. Activity G is on the critical path. d. Activity G takes 2 days to complete.

answer
Answers: 2

Other questions on the subject: Business

image
Business, 21.06.2019 19:20, sam10146
Chester has a credit score of 595 according to the following table his credit rating is considered to be which of these
Answers: 1
image
Business, 21.06.2019 22:40, gobertbrianna40
Job a3b was ordered by a customer on september 25. during the month of september, jaycee corporation requisitioned $2,400 of direct materials and used $3,900 of direct labor. the job was not finished by the end of the month, but needed an additional $2,900 of direct materials in october and additional direct labor of $6,400 to finish the job. the company applies overhead at the end of each month at a rate of 100% of the direct labor cost. what is the amount of job costs added to work in process inventory during october?
Answers: 3
image
Business, 22.06.2019 12:50, 20170020
Kyle and alyssa paid $1,000 and $4,000 in qualifying expenses for their two daughters jane and jill, respectively, to attend the university of california. jane is a sophomore and jill is a freshman. kyle and alyssa's agi is $135,000 and they file a joint return. what is their allowable american opportunity tax credit after the credit phase-out based on agi is taken into account?
Answers: 1
image
Business, 22.06.2019 18:00, Aethis
Biochemical corp. requires $600,000 in financing over the next three years. the firm can borrow the funds for three years at 10.80 percent interest per year. the ceo decides to do a forecast and predicts that if she utilizes short-term financing instead, she will pay 7.50 percent interest in the first year, 12.15 percent interest in the second year, and 8.25 percent interest in the third year. assume interest is paid in full at the end of each year. a)determine the total interest cost under each plan. a) long term fixed rate: b) short term fixed rate: b) which plan is less costly? a) long term fixed rate plan b) short term variable rate plan
Answers: 2
Do you know the correct answer?
Assume that activity G has the following times: Early start time 7 days Early finish time 13 days La...

Questions in other subjects:

Konu
Spanish, 04.05.2021 20:40
Konu
Social Studies, 04.05.2021 20:40
Konu
Mathematics, 04.05.2021 20:40
Konu
Mathematics, 04.05.2021 20:40