for the "determine data needs" activity of a project, the optimistic estimated duration is 10 days, the pessimistic estimated duration is 20 days, the most likely time is 15 days. what is the expected duration of completing this activity?

answer
Answers: 3

Other questions on the subject: Physics

image
Physics, 21.06.2019 19:30, yolinda123429
Molten iron fills a mould, which has a volume of 200 cm cubed. calculate the volume when the iron cools and solidifies.
Answers: 1
image
Physics, 22.06.2019 08:20, mimithurmond03
The bubba chump shrimp company processes and packages shrimp for sale to wholesale seafood distributors. the shrimp are transported to the main plant by trucks that carry 1,000 pounds (lb) of shrimp. once the continuous flow processing of the shrimp begins, no inventory is allowed in buffers due to spoilage and all of the shrimp must be processed within 12 hours to prevent spoilage. the processing begins at the sorter, where the trucks dump the shrimp onto a conveyor belt that feeds into the sorter, which can sort up to 500 lb per hour. the shrimp then proceed to the desheller, which can process shrimp at the rate of 400 lb per hour. however, after 3 hours and 45 minutes of processing, the desheller must be stopped for 15 minutes to clean out empty shrimp shells that have accumulated. the veins of the shrimp are then removed in the deveining area at a maximum rate of 360 lb per hour. the shrimp proceed to the washing area, where they are processed at 750 lb per hour. finally, the shrimp are packaged and frozen. what is the daily process capacity of the processing plant (excluding the packaging and freezing)?
Answers: 2
image
Physics, 22.06.2019 09:30, anytka21ovxqoa
How would a small bar magnet be oriented when placed at position x?
Answers: 2
image
Physics, 22.06.2019 10:10, sadie960
Aclarinetist, setting out for a performance, grabs his 3.350 kg clarinet case (including the clarinet) from the top of the piano and carries it through the air with an upward force of 24.65 n. find the case's vertical acceleration. indicate an upward acceleration as positive and a downward one as negative.
Answers: 1
Do you know the correct answer?
for the "determine data needs" activity of a project, the optimistic estimated duration is 10 days,...

Questions in other subjects:

Konu
Mathematics, 23.07.2020 22:01
Konu
Mathematics, 23.07.2020 22:01