Mathematics, 23.07.2019 03:00, peagwatyourservice

An electrician was hired to wire a new house. in 11 1/4 days he estimates he has completed 70% of the job. at his current pace of work, how long will it take him to complete the entire job?

answer
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 14:30, kadrian12
Graph the system: f(x)= 3/x-2; f(x)= 1/2x + 2
Answers: 3
image
Mathematics, 21.06.2019 19:00, wannaoneisforever
What numbers are included in the set of integers? what numbers are not included?
Answers: 2
image
Mathematics, 22.06.2019 00:30, brittsterrr
When you flip a biased coin the probability of getting a tail is 0.6. how many times would you expect to get tails if you flip the coin 320 times?
Answers: 1
image
Mathematics, 22.06.2019 02:30, lieunekop8fm90
The center on a target has a diameter of 5 inches. the whole target has a diameter of 25 inches. complete the explanation for what part of the whole target is the center. the center of the target takes up % of the whole target.
Answers: 3
Do you know the correct answer?
An electrician was hired to wire a new house. in 11 1/4 days he estimates he has completed 70% of th...

Questions in other subjects:

Konu
Spanish, 11.11.2020 17:30