All the members of a construction crew work at the same pace. six of them working together are able to pour foundation in 22 hours. how many hours would this job take if the number of workers: decreased by factor of 2

answer
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 21:20, burners
What is the area of a triangle with vertices at (-3 3) (-3,2) and (1,2)?
Answers: 1
image
Mathematics, 21.06.2019 21:50, nena4200
Solve the following pair of equations for x and y: ax/b_ by /a= a +b; ax - by = 2ab
Answers: 2
image
Mathematics, 21.06.2019 22:30, cordobamariana07
The difference of three and the reciprocal of a number is equal to the quotient of 20 and the number. find the number.
Answers: 2
image
Mathematics, 22.06.2019 00:00, kimberly185
In a timed typing test lara typed 63 words per minute. estimate the number of words she should be able to type in half in hour show your work
Answers: 2
Do you know the correct answer?
All the members of a construction crew work at the same pace. six of them working together are able...

Questions in other subjects:

Konu
Mathematics, 21.01.2021 19:00