6men can complete a job in 20 days. if the men work at the same rate. how many more are needed to complete the job in 12 days

answer
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 18:50, lolh1520
What are the values of a, b, and c in the quadratic equation 0 = x2 – 3x - 2? a = 1, b = 3, c = 2 a=, b = -3,c=-2 a = 1, b = 3, c= 2 a = 1.0= -3, c = 2
Answers: 2
image
Mathematics, 21.06.2019 20:30, amandaaaa13
Asmall business produces and sells balls. the fixed costs are $20 and each ball costs $4.32 to produce. each ball sells for $8.32. write the equations for the total cost, c, and the revenue, r, then use the graphing method to determine how many balls must be sold to break even.
Answers: 1
image
Mathematics, 21.06.2019 22:00, fatherbamboo
Worth 100 points need the answers asap first row -x^2 2x^2 (x/2)^2 x^2 x is less than 2 x is greater than 2 x is less than or equal to 2 x is greater than or equal to 2 second row -5 -5/2 4 5 •2 is less than x& x is less than 4 •2 is less than or equal to x & x is less than or equal to 4 •2 is less than or equal to x& x is less than 4 •2 is less than x& x is less than or equal to 4
Answers: 2
image
Mathematics, 22.06.2019 00:00, destinywashere101
Last week jason walked 3 1/4 miles each day for 3 days and 4 5/8 miles each day for 4 days. about how many miles did jason walk last week?
Answers: 1
Do you know the correct answer?
6men can complete a job in 20 days. if the men work at the same rate. how many more are needed to co...

Questions in other subjects:

Konu
Chemistry, 22.05.2020 19:06
Konu
History, 22.05.2020 19:06