In this question assume that all the men work for the same hours and at the same
work rate.
...
Mathematics, 10.03.2022 15:10, LSDWW123w
In this question assume that all the men work for the same hours and at the same
work rate.
A builder estimates 5 men would need 12 days to complete the job.
What would his estimate be for 4 men to complete the same job?
You must show your working.