Direct Labor Variances
Ada Clothes Company produced 20,000 units during April. The Cutting Department used 3,800 direct labor hours at an actual rate of $13.30 per hour. The Sewing Department used 6,300 direct labor hours at an actual rate of $13.00 per hour. Assume there were no work in process inventories in either department at the beginning or end of the month. The standard labor rate is $13.20. The standard labor time for the Cutting and Sewing departments is 0.2 hour and 0.3 hour per unit, respectively.
a. Determine the direct labor rate, direct labor time, and total direct labor cost variance for the (1) Cutting Department and (2) Sewing Department. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
Cutting Department Sewing Department
Direct Labor Rate Variance $fill in the blank 1
$fill in the blank 3
Direct Labor Time Variance $fill in the blank 5
$fill in the blank 7
Total Direct Labor Cost Variance $fill in the blank 9
$fill in the blank 11
b. The two departments have opposite results. The Cutting Department has a(n)
rate variance and a(n)
time variance, resulting in a total
cost variance. In contrast, the Sewing Department has a(n)
Answers: 3
Mathematics, 21.06.2019 20:40, selenamr
Formulate the indicated conclusion in nontechnical terms. be sure to address the original claim. the foundation chair for a hospital claims that the mean number of filled overnight beds is over 523, and she is therefore justified starting a funding campaign to add a wing to the hospital. assuming that a hypothesis test has been conducted and that the conclusion is failure to reject the null hypothesis, state the conclusion in nontechnical terms.
Answers: 3
Mathematics, 21.06.2019 23:00, lejeanjamespete1
Graph the system of equations. {6x−4y=−244x−8y=−32 use the line tool to graph the lines.
Answers: 1
Mathematics, 22.06.2019 01:00, saigeshort
Pentagon abcde is dilated according to the rule do,3(x, y) to create the image pentagon a'b'c'd'e', which is shown on the graph. what are the coordinates of point a of the pre-image? a) (-1, 1)b) (-1, 2)c) (-9, 6)d) (-9, 18)
Answers: 3
Mathematics, 22.06.2019 01:30, musfirahkhurram
Sara is flying a kite at the park. the angle of elevation from sara to kite in the sky is 53° and the length of the string is 32 feet. of sara is 5 feet tall how far off the ground is the kite
Answers: 1
Direct Labor Variances
Ada Clothes Company produced 20,000 units during April. The Cutting Departm...
Computers and Technology, 23.03.2021 14:00
Physics, 23.03.2021 14:00