Mathematics, 15.12.2021 01:10, Paris4life
A tube well is bored 800 meters deep. The 1st meter costs $250 and the cost per meter increases by $50 for every subsequent meter. Find the cost of boring the 750th meter. Do not use commas or symbols in your answer.
Answers: 1
Mathematics, 21.06.2019 19:30, estherstlouis7812
1. find the area of the unshaded square 2. find the area of the large square 3. what is the area of the frame represented by the shaded region show
Answers: 1
Mathematics, 21.06.2019 22:00, yay47
Worth 100 points need the answers asap first row -x^2 2x^2 (x/2)^2 x^2 x is less than 2 x is greater than 2 x is less than or equal to 2 x is greater than or equal to 2 second row -5 -5/2 4 5 •2 is less than x& x is less than 4 •2 is less than or equal to x & x is less than or equal to 4 •2 is less than or equal to x& x is less than 4 •2 is less than x& x is less than or equal to 4
Answers: 1
Mathematics, 21.06.2019 23:00, tonimgreen17p6vqjq
Which graph represents the linear function below? y-3=1/2(x+2)
Answers: 2
A tube well is bored 800 meters deep. The 1st meter costs $250 and the cost per meter increases by $...