Mathematics, 15.12.2021 01:10, Paris4life

A tube well is bored 800 meters deep. The 1st meter costs $250 and the cost per meter increases by $50 for every subsequent meter. Find the cost of boring the 750th meter. Do not use commas or symbols in your answer.

answer
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 18:00, ciara180
Place the following steps in order to complete the square and solve the quadratic equation,
Answers: 1
image
Mathematics, 21.06.2019 19:30, estherstlouis7812
1. find the area of the unshaded square 2. find the area of the large square 3. what is the area of the frame represented by the shaded region show
Answers: 1
image
Mathematics, 21.06.2019 22:00, yay47
Worth 100 points need the answers asap first row -x^2 2x^2 (x/2)^2 x^2 x is less than 2 x is greater than 2 x is less than or equal to 2 x is greater than or equal to 2 second row -5 -5/2 4 5 •2 is less than x& x is less than 4 •2 is less than or equal to x & x is less than or equal to 4 •2 is less than or equal to x& x is less than 4 •2 is less than x& x is less than or equal to 4
Answers: 1
image
Mathematics, 21.06.2019 23:00, tonimgreen17p6vqjq
Which graph represents the linear function below? y-3=1/2(x+2)
Answers: 2
Do you know the correct answer?
A tube well is bored 800 meters deep. The 1st meter costs $250 and the cost per meter increases by $...

Questions in other subjects:

Konu
Social Studies, 27.06.2019 18:30
Konu
English, 27.06.2019 18:30