Question 4 (5 marks) To restore a vintage train, 13 activities need to be completed. The network below shows these 13 activities and their completion times in hours. C,6 G, 3 4,5 1D, 2 H,4 K,7 E, 2 L, 3 start finish B, 5 F,4 1,3 *M,6 J, 2 a. Determine the earliest starting time of activity F.

The minimum time in which all 13 activities can be completed is 21 hours.
b. What is the latest starting time of activity L?

C. What is the float time of activity J?

Just before they started restoring the train, the members of the club needed to add another activity, X, to the project Activity X will take seven hours to complete. Activity X has no predecessors, but must be completed before activity G starts.
d. What is the latest starting time of activity Xif it is not to increase the minimum completion time of the project? 1 mark​

answer
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 14:30, mcouil9369
Which functions are even? check all of the boxes that apply. f(x) = x4 – x? f(x) = x2 – 3x + 2 f(x) = (x - 2) f(x) = x done
Answers: 3
image
Mathematics, 21.06.2019 19:30, bakaoffire
Mr. brettler is hanging up a 5-foot tall rectangular welcome sign in the gym. he has drawn a sketch on a coordinate grid. he has the lower vertices of the sign at (9, –3) and (–6, –3). where would the upper vertices be on the grid?
Answers: 1
image
Mathematics, 21.06.2019 22:40, 721345
What is the the greatest common factor ?
Answers: 2
image
Mathematics, 21.06.2019 23:20, emilypzamora11
Find the common ratio of the sequence. -4, 8, -16, 32, a: -12b: -2c: 12d: -1/-2
Answers: 1
Do you know the correct answer?
Question 4 (5 marks) To restore a vintage train, 13 activities need to be completed. The network bel...

Questions in other subjects:

Konu
Mathematics, 02.11.2020 05:20
Konu
English, 02.11.2020 05:20
Konu
Biology, 02.11.2020 05:20