32 workers can complete a work in 30 days working 6 hours per day. How many days are required to complete the same work by 16 workers working 8 hours per day?

answer
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 21:00, cwebb4383
The sum of the first eight terms of an arithmetic progression is 9m + 14. the fifth term of the06 progression is 2m - 6, where m is a constant. given that the first term of the progression is 26,find the value of the common difference, d and thevalue of m.
Answers: 1
image
Mathematics, 21.06.2019 22:50, ciaotaylor
1. if events a and b are non-overlapping events, how do you find the probability that one or the other occurs? 2. what does it mean if p(a or b) equals 1?
Answers: 2
image
Mathematics, 21.06.2019 23:00, princessroseee769
40 points. given: two congruent angles ∠c and ∠r are supplementary. prove: ∠r and ∠c are both right angles. it doesn't have to be exactly 10 rows. statements reasons1. 1. 2. 2. 3. 3. 4. 4. 5. 5. 6. 6. 7. 7. 8. 8. 9. 9. 10. 10.
Answers: 2
image
Mathematics, 22.06.2019 00:30, andy963936
The measures of two supplementary angles are (2x + 10)° and (8x + 10)°. what is the measure of the larger angle? a. 16° b. 44° c. 14° d. 138°
Answers: 2
Do you know the correct answer?
32 workers can complete a work in 30 days working 6 hours per day. How many days are required to com...

Questions in other subjects:

Konu
Chemistry, 23.05.2021 03:40