Mr. X and Mr. Y, when work together, run out installing floor tiles a room in 6 day. When Mr. X works himself, he took time 5 days less than from Mr. Y who work alone. How much time Mr. X and Mr. Y take to spend this work itself without help?​

answer
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 12:50, jdvazquez18p7a7vs
Identify the parent function that can be used to graph the function f(x)= (1/4x)^3
Answers: 1
image
Mathematics, 21.06.2019 13:30, igtguith
Franklin neason earns $5,250 a month as a sales manager. what is his semimonthly salary? a.$10,500b.$5,250c.$2,365d.$2,625
Answers: 1
image
Mathematics, 22.06.2019 00:20, soystersoce
When steve woke up. his temperature was 102 degrees f. two hours later it was 3 degrees lower. what was his temperature then?
Answers: 1
image
Mathematics, 22.06.2019 01:00, suicune19
Find the measure for the angle indicated in bold
Answers: 1
Do you know the correct answer?
Mr. X and Mr. Y, when work together, run out installing floor tiles a room in 6 day. When Mr. X work...

Questions in other subjects: