This table shows the relationship between the number of workers assigned to a project and the number of days it will take them to complete the project. Workers Days
2 42
3 28
6 14
12 7

Use the relationship in the table to complete the statements.
Select the correct answer from each drop-down menu.

As the number of workers increases, the number of days it will take to complete the project _. The _ of the two variables is constant.

The number of days it takes for a construction project to be completed varies _ as the number of workers assigned to the project.


This table shows the relationship between the number of workers assigned to a project and the numbe

answer
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 21:00, ally7366
Roger could feed 5 walruses with 4 kilograms of fish. how many walruses could he feed with 7.2 kilograms of fish?
Answers: 1
image
Mathematics, 21.06.2019 21:00, wytchnia
List x1, x2, x3, x4 where xi is the midpoint endpoint of the five equal intervals used to estimate the area under the curve of f(x) between x = 0 and x = 10.
Answers: 1
image
Mathematics, 21.06.2019 21:20, andybiersack154
52 cm radius = diameter = area = circumference = circumfer
Answers: 1
image
Mathematics, 22.06.2019 01:00, autumnrose02
Anew landowner is interested in constructing a fence around the perimeter of her property. her property is 1,080√30 feet wide and 500√20 feet long. what is the perimeter of the property? (recall that the perimeter is the sum of each side of a shape or boundary). a 1,580√40 feet b. 5,320√5 feet c. 3,160√20 feet d. 10,640√5 feet
Answers: 3
Do you know the correct answer?
This table shows the relationship between the number of workers assigned to a project and the number...

Questions in other subjects: