Mathematics, 21.07.2021 20:50, payshencec21
This table shows the relationship between the number of workers assigned to a project and the number of days it will take them to complete the project.
Workers Days
2 42
3 28
6 14
12 7
Use the relationship in the table to complete the statements.
Select the correct answer from each drop-down menu.
As the number of workers increases, the number of days it will take to complete the project _. The _ of the two variables is constant.
The number of days it takes for a construction project to be completed varies _ as the number of workers assigned to the project.
Answers: 2
Mathematics, 21.06.2019 21:20, andybiersack154
52 cm radius = diameter = area = circumference = circumfer
Answers: 1
Mathematics, 22.06.2019 01:00, autumnrose02
Anew landowner is interested in constructing a fence around the perimeter of her property. her property is 1,080β30 feet wide and 500β20 feet long. what is the perimeter of the property? (recall that the perimeter is the sum of each side of a shape or boundary). a 1,580β40 feet b. 5,320β5 feet c. 3,160β20 feet d. 10,640β5 feet
Answers: 3
This table shows the relationship between the number of workers assigned to a project and the number...
Mathematics, 24.06.2019 07:00
Mathematics, 24.06.2019 07:00
Chemistry, 24.06.2019 07:00