A group of 40 workers can do a construction in 16 days. When has elapsed 4 days, 10 workers retired. How many days of delay the construction will be delivered?

answer
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 14:30, Elliewop
What is the distance between (–2 1/2,-3) and (1, –3)?
Answers: 1
image
Mathematics, 21.06.2019 15:20, gibbss80stu
Find the image of a(4, -2) after it is reflected over the line y= 2, then reflected over the line x = 2. (-8,6) o (0.-2) o (0,6) (-8, -2)
Answers: 1
image
Mathematics, 21.06.2019 16:30, hector87
The label on the car's antifreeze container claims to protect the car between ? 40°c and 125°c. to convert celsius temperature to fahrenheit temperature, the formula is c = 5 over 9 (f ? 32). write and solve the inequality to determine the fahrenheit temperature range at which this antifreeze protects the car. ? 40 > 5 over 9 (f ? 32) > 125; ? 40 > f > 257 ? 40 < 5 over 9 (f ? 32) < 125; ? 40 < f < 257 ? 40 < 5 over 9 (f ? 32); ? 40 < f 5 over 9 (f ? 32) < 125; f < 257
Answers: 2
image
Mathematics, 21.06.2019 17:40, sophiateaches053
If sec theta = 5/3 and the terminal point determined by theta is in quadrant 4, then
Answers: 1
Do you know the correct answer?
A group of 40 workers can do a construction in 16 days. When has elapsed 4 days, 10 workers retired....

Questions in other subjects:

Konu
English, 04.12.2021 01:10
Konu
English, 04.12.2021 01:10