The Shredder, Inc. produces two types of paper shredders, home and office. The office model requires 4 hours to assembly and 6 finishing work units for finishing work, the home model requires 3 hours to
assemble and 6 finishing work units for finishing. The maximum number of assembly hours available is 72
per day, and the maximum number of finishing hours available is 132 per day.
Let 2 = the number of office model shredders produced per day and y = the number of home model
shredders produced per day.
Write the system of inequalities that represents the maximum number of shredders that can be produced in
one day.
NOTE: 4 inequalities are expected.
572
< 132

answer
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 16:30, erbnichole
Solve by any method (graphing, substitution or linear combination)y = x - 82x + 3y = 1a) (2, -6)b) (5, -3)c) (4, -4)d) (0, -8)i figured it out. the answer is (5, -3)
Answers: 1
image
Mathematics, 21.06.2019 18:00, duplerk30919
What is the difference between the predicted value and the actual value
Answers: 1
image
Mathematics, 21.06.2019 20:40, vanitycarraway2000
Which table represents points on the graph of h(x) = 3√-x+2?
Answers: 3
image
Mathematics, 21.06.2019 23:30, isabel2417
Which equation represents a direct linear variationa. y=x2b. y=2/5xc. y=1/xd. y=x+3
Answers: 3
Do you know the correct answer?
The Shredder, Inc. produces two types of paper shredders, home and office. The office model requires...

Questions in other subjects:

Konu
History, 12.03.2020 21:56