A project has the following activities and related data: Activity. Time (Weeks) Immediate Activity Predecessor Crash Most Most Most Cost Maximum Optimistic likely Pessimistic ($000) Crashable (a) (m) (C) per weeks week A None 1 3 11 3 1 00 None 4 5 6 4 1 С А 5 6 7 1 2 D А 4 5 12 1 2 1 E B 6 11 2 1 B 1 2 15 F 1 3 2 4 6 6 G CD 2 3 4 2 1 2 H EF G CD 2 4 6 6 N H EF 2 3 3 4 4 2 1 34a. (20 points) a. Compute the expected value E(t) and variance V(t) for all activities
Activity A B C D E F G H
E(t) weeks
V(t) weeks^2
b. there are three critical paths ACG, ADG, and BEH, all with expected project completion time time E(t) = 14 weeks. Compute the variance of project completion time for each path
V(ACG)=
V(ADG)=
V(BEH)
c. Assume that the project completion time T is normally distributed with mean E(T)=14 weeks and variance V(T) approximately by the maximum of the variances of the three individual critical paths. Determine the time X in weeks for which there is a 40% probability that the project can be completed on or before x.
d. List all alternatives and the respective costs for shortening the project by one week and identify the best alternative that has the minimum costs. Hint there are 8 alternatives
Alternative cost
the best alternative is..
e. For activity i, let Xi be the earliest finishing time and Yi be the number of weeks shortened. Formulate the linear program for minimizing the cost for shortening the project by one week

answer
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 17:00, agerald
Measures of the angle of r, 31 s (x+4) t (3x+9)
Answers: 1
image
Mathematics, 21.06.2019 19:50, keigleyhannah30
Use composition to determine if (x) or h(x) is the inverse of f(x) for the limited domain x2-1.
Answers: 3
image
Mathematics, 21.06.2019 20:00, lucerogon7403
How can you construct perpendicular lines and prove theorems about perpendicular lines
Answers: 3
image
Mathematics, 22.06.2019 00:30, amc9639
Ican interpret and represent the remainder in division calculations sensibly for the context (eg if we wont to know how many 40 seat buses will be needed to transport 170 students for on excursion, we divide 170 by 40 and realise buses and another smaller vehicle to that we need 4 transport 10 more students) solve the following questions. show your work! 11) the zoo had 420 butterflies that needed to be transported to a new enclosure. the boxes that the butterflies would be moved in only hold 80 butterflies in each. how many boxes would they need? 2 12) each classroom in the school can have exactly 25 students, if there are 345 students in the school how many full classrooms are there?
Answers: 2
Do you know the correct answer?
A project has the following activities and related data: Activity. Time (Weeks) Immediate Activity P...

Questions in other subjects:

Konu
Mathematics, 04.09.2019 22:20