Mathematics, 25.05.2021 03:50, maddieb1011

The film The Lord of the Rings: The Return of the King, the last installment of The Lord of the Rings trilogy, was directed by Peter Jackson and released on December 17 2003 in the U. S. with huge success. Eventually, the film won 11 Oscars for all of its nominations. The film's box office has been more than $1 billion. In the film, there are long sequences in which not all main characters appear at the same time. And there are big scenes where everybody shows up. Thinking about the making of the film, behind the scenes, we can hypothetically break down the entire cinematic project into the following aggregate activities (We assume away all the complexities in shooting the three installments at the same time and other production details): ‐ Plan, screenplay, finance, cast, film crew, location
‐ Construction of movie sets
‐ Shooting sequence 1
‐ Shooting sequence 2
‐ Shooting sequence 3
‐ Big scene sequence
‐ Post‐production & finalization before release
We have the following hypothetical data on time in months and cost in millions of dollars:
ID IP T ES EF LS LF SLK NT NC CT CC CCR
A ‐ 6.0 6.0 13.0 6.0 13.0
B A 4.0 4.0 9.0 3.0 12.0
C B 4.0 4.0 12.0 4.0 12.0
D B 5.0 11.0 5.0 14.0 4.0 16.0
E B 6.0 0.0 6.0 16.0 4.0 19.0
F C, D,E4.0 4.0 19.0 4.0 19.0
G F 6.0 6.0 11.0 5.0 13.5
Note: IP = Immediate Predecessor; T = NT = Normal Time; ES = Earliest Start; EF = Earliest Finish; LS = Latest Start; LF = Latest Finish; SLK = Slack Time; NT = Normal Time; NC = Normal
Cost; CT = Crash Time; CC = Crash Cost; & CCR = Crash Cost/Time Unit (Crash Cost Rate).
Copy the table to your homework and complete the following parts:
By looking at the chart in part (a), find all possible paths through the network with their corresponding path times. Based on these path times, determine the critical path.
Based on part (a) By using the forward and backward passes together with the four time determination rules, fill your calculations for ES,
EF, LS, LF, and SLK in the appropriate cells.
(b) [2] Try to independently fill in the columns ES, EF, LS, LF, and SLK of the table. If you have difficulties, refer to part (a). Determine the activity with the most slack time.
c) [2] Based on part (a), find the critical path by going through the activities with no slack time.
Compare this result with the critical path found in part (b).
d) Use appropriate data to compute crash costs per time unit and fill in the CCR column. Cross out any CCR cells where the corresponding activities cannot be crashed.
(e) [2] Find the total normal cost of the film. Find the normal cost on the original critical path. Compute the cost proportion of the critical path in the film's budget.

answer
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 20:00, myparentsrock17
Given ab and cb are tangents of p, and m =10°. what is the measure of abp?
Answers: 1
image
Mathematics, 21.06.2019 22:00, marissastewart533
Given sin∅ = 1/3 and 0 < ∅ < π/2 ; find tan2∅ a. (4√2)/9 b. 9/7 c. (4√2)/7 d.7/9
Answers: 2
image
Mathematics, 21.06.2019 22:30, sanociahnoel
Ibeg you to me 20. a reaction produces 4.93 l of oxygen, but was supposed to produce 1 mol of oxygen. what is the percent yield?
Answers: 3
image
Mathematics, 22.06.2019 02:00, b2cutie456
Emily convinced her mom to buy a giant box of her favorite cereal. her mom doesn't think the box will fit on their shelf. the volume of the box is 1000 cm^3 . the base of the box is 25 cm by 10 cm
Answers: 1
Do you know the correct answer?
The film The Lord of the Rings: The Return of the King, the last installment of The Lord of the Ring...

Questions in other subjects:

Konu
Mathematics, 21.10.2019 17:30