1. The manager of the Oak Hills Swimming Club is planning the club’s swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows: (Marks 4) Activity Description Predecessor Optimistic Most Probable Pessimistic
A Meet with board - 1 1 2
B Hire coaches A 4 6 8
C Reserve pool A 2 4 6
D Announce program B, C 1 2 3
E Meet with coaches B 2 3 4
F Order team suit A 1 2 3
G Register swimmers D 1 2 3
H Collect fees G 1 2 3
I Plan first practice E, H, F 1 1 1

a. Draw a project network. Develop an activity schedule.
b. What are the critical activities, and what is the expected project completion time?
c. If the club manager plans to start the project on February 1, what is the probability the swimming program will be ready by the scheduled May 1 date (13 weeks)? Should the manager begin planning the swimming program before February 1

answer
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 14:40, reginaldboyd28
What is the celsius temperature that is equal to 94 degrees fahrenheit using the formula f=9/5 c+32
Answers: 2
image
Mathematics, 22.06.2019 00:30, mdaniella522
Sawsan recorded the favorite sport of students at her school. she surveyed 200 students. how many students chose tennis?
Answers: 2
image
Mathematics, 22.06.2019 03:00, karenjunior
In the figure, triangle aob and triangle boc form a linear pair ,find the measure of x
Answers: 3
image
Mathematics, 22.06.2019 04:40, mommatann
Write an equation in slope-intercept form using the given points (19,-16), (-7,-15)
Answers: 1
Do you know the correct answer?
1. The manager of the Oak Hills Swimming Club is planning the club’s swimming team program. The firs...

Questions in other subjects:

Konu
Mathematics, 05.02.2021 01:00