Mathematics, 23.05.2021 04:50, leslymejiaquiroz1

12 workers can do a piece of work in 20 days, how many worker should
be added to complete the work in 16 days? [Ans: 3]

If you help me to do this question I will make brainliest​

answer
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 20.06.2019 18:04, matius0711
Plz i want answer and i would appreciate it is is a b c or d
Answers: 1
image
Mathematics, 21.06.2019 18:00, rick4763
When lulu enlarged her drawing of a rabbit, the enlarged picture appeared to be distorted. which statement about the transformation applied to her drawing is true?
Answers: 2
image
Mathematics, 21.06.2019 18:10, ab2019
Drag the tiles to the boxes to form correct pairs. not all tiles will be used. match each set of vertices with the type of quadrilateral they form
Answers: 3
image
Mathematics, 21.06.2019 21:00, jennybee12331
Louis wants to carpet the rectangular floor of his basement the basement has an area of 864 square feet the width of the basement is 2/3 its length what is the length of lewis's basement
Answers: 2
Do you know the correct answer?
12 workers can do a piece of work in 20 days, how many worker should
be added to complete the...

Questions in other subjects: