Mathematics, 17.05.2021 01:00, jamarhroul
In order to complete a large job, 1000 workers were hired, just enough to complete the job on schedule. All the workers stayed on the job while the first quarter of the work was done, so the first quarter of the work was completed on schedule. Then 100 workers were laid off, so the second quarter of the work was completed behind schedule. Then an additional 100 workers were laid off, so the third quarter of the work was completed still further behind schedule. Given that all workers work at the same rate, what is the minimum number of additional workers, beyond the 800 workers still on the job at the end of the third quarter, that must be hired after three-quarters of the work has been completed so that the entire project can be completed on schedule or before?
Answers: 1
Mathematics, 21.06.2019 17:40, JessicaSontay8841
Follow these steps using the algebra tiles to solve the equation −5x + (−2) = −2x + 4. 1. add 5 positive x-tiles to both sides and create zero pairs. 2. add 4 negative unit tiles to both sides and create zero pairs. 3. divide the unit tiles evenly among the x-tiles. x =
Answers: 2
Mathematics, 21.06.2019 20:10, sawyerharper
Which expression do you get when you eliminate the negative exponents of 4a^2 b^216a^-3 b
Answers: 3
In order to complete a large job, 1000 workers were hired, just enough to complete the job on schedu...
Social Studies, 06.03.2021 23:00
Mathematics, 06.03.2021 23:00
Physics, 06.03.2021 23:00
Mathematics, 06.03.2021 23:00
Biology, 06.03.2021 23:00