Acarpenter estimates that it will take one person 54 hours to complete a job he plans to have three people work on the job for two days how many hours each day will the workers need to work to complete the job

answer
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 16:00, blackwhiteroses383
Which graph represents the solution set for the given system of inequalities? x+2y< 3 x+y> 4 3x-2y> 4
Answers: 2
image
Mathematics, 21.06.2019 17:30, lizzy2951
Someone this asap for a group of students attends a basketball game. * the group buys x hot dogs at the concession stand for $2 each. * the group buys y drinks at the concession stand for $3 each. the group buys 29 items at the concession stand for a total of $70. how many hot dogs did the group buy?
Answers: 2
image
Mathematics, 21.06.2019 18:50, savskye1767
What statement is true? 2x^2-9x+2=-1
Answers: 1
image
Mathematics, 21.06.2019 19:10, gurlnerd
1jessica's home town is a mid-sized city experiencing a decline in population. the following graph models the estimated population if the decline continues at the same rate. select the most appropriate unit for the measure of time that the graph represents. a. years b. hours c. days d. weeks
Answers: 2
Do you know the correct answer?
Acarpenter estimates that it will take one person 54 hours to complete a job he plans to have three...

Questions in other subjects:

Konu
Mathematics, 20.03.2020 02:18