The following is a table of activities associated with
a project at rafay ishfaq’s software firm in chicago, their durations,
and what activities each must precede:
activity duration (weeks) precedes
a (start) 1 b, c
b 1 e
c 4 f
e 2 f
f (end) 2 —
a) draw an aon diagram of the project, including activity durations.
b) define the critical path, listing all critical activities in chronological
order.
c) what is the project duration (in weeks)?
d) what is the slack (in weeks) associated with any and all noncritical
paths through the project?

answer
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 15:30, sydneyglover302
What is the length of the missing leg in this right triangle? 18 mm 24 mm 26 mm 32 mm
Answers: 1
image
Mathematics, 21.06.2019 18:00, lovemykay2355
If f(x) = 4x – 3 and g(x) = 8x + 2, find each function value a. f[g(3)] b. g[f(5)] c. g{f[g(-4)]}
Answers: 3
image
Mathematics, 21.06.2019 21:30, kristinashau
If you flip a coin 3 times, what is the probability of flipping heads 3 times? a. p(3 heads) = 3/8 b. p(3 heads) = 1/6 c. p(3 heads) = 1/8 d. p(3 heads) = 1/2
Answers: 2
image
Mathematics, 22.06.2019 01:30, jude40
Asample of 200 rom computer chips was selected on each of 30 consecutive days, and the number of nonconforming chips on each day was as follows: the data has been given so that it can be copied into r as a vector. non. conforming = c(10, 15, 21, 19, 34, 16, 5, 24, 8, 21, 32, 14, 14, 19, 18, 20, 12, 23, 10, 19, 20, 18, 13, 26, 33, 14, 12, 21, 12, 27) #construct a p chart by using the following code. you will need to enter your values for pbar, lcl and ucl. pbar = lcl = ucl = plot(non. conforming/200, ylim = c(0,.5)) abline(h = pbar, lty = 2) abline(h = lcl, lty = 3) abline(h = ucl, lty = 3)
Answers: 3
Do you know the correct answer?
The following is a table of activities associated with
a project at rafay ishfaq’s software fi...

Questions in other subjects: