Mathematics, 31.08.2019 14:00, queenkimm26

Two companies working together can clear a parcel of land in 7 hours. working alone, it would take company a 4 hours longer to clear the land than company
b. how ong would it take company b to clear the parcel of land alone

answer
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 14:40, beebeck6573
Chose the graph below that represents the following system of inequality’s
Answers: 2
image
Mathematics, 21.06.2019 15:50, shamiahG
Which statement accurately explains whether a reflection over the x-axis and a 180° rotation would map figure acb onto itself?
Answers: 2
image
Mathematics, 21.06.2019 21:30, hwest98
Aye asap pls ! markin da brainiest too ! btw da step choices are all add, distribute, divide, n subtract
Answers: 2
image
Mathematics, 21.06.2019 21:40, chunkymonkey090
Ihonestly have no clue if it's each or none.
Answers: 1
Do you know the correct answer?
Two companies working together can clear a parcel of land in 7 hours. working alone, it would take c...

Questions in other subjects:

Konu
Business, 21.08.2021 15:50
Konu
English, 21.08.2021 15:50
Konu
Physics, 21.08.2021 15:50
Konu
Chemistry, 21.08.2021 15:50
Konu
Mathematics, 21.08.2021 15:50