A contractor employed 60 men to do a certain job in 15 days. How
many laborers working at the same
rate could complete the work in 4
days?​

answer
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 14:40, leannesmith90101
Sara sells beaded necklaces she makes a profit of 4 dollars pn every neclace she sells which table represents the profit sara makes
Answers: 1
image
Mathematics, 21.06.2019 19:00, kkatlynn
The diagonals of a quadrilaretral intersect at (-1,4). one of the sides of the quadrilateral is bounded by (2,7) and (-3,5) determine the coordinates of the other side in order for the quadrilaretral to be a square.
Answers: 1
image
Mathematics, 21.06.2019 22:00, prelogical
Onnie is considering doing some long term investing with money that she inherited. she would like to have $50,000 at the end of 30 years. approximately how much money would lonnie need to put into an account earning 6% interest compounded annually in order to meet her goal?
Answers: 1
image
Mathematics, 21.06.2019 22:20, Kode19001
Which of the following describes how to translate the graph y = |x| to obtain the graph of y = |x+1|+1? shift 1 unit left and 1 unit down shift 1 unit left and 1 unit up shift 1 unit night and 1 unit down shift 1 unit nght and 1 unit up
Answers: 1
Do you know the correct answer?
A contractor employed 60 men to do a certain job in 15 days. How
many laborers working at the...

Questions in other subjects:

Konu
Health, 02.12.2020 19:00
Konu
Social Studies, 02.12.2020 19:00