Mathematics, 15.04.2021 04:50, destinee8863

A company makes a product in two different factories. At Factory X it takes 30 hours to produce the product and at Factory Y it takes 20 hours. The
costs of producing these items are $40 at Factory X and $60 at Factory Y.
The company's labor force can provide 6000 hours of labor each week and
resources are $12,000 each week. Factory X can only produce a maximum
of 120 products in a week. The company makes a profit of $100 from the
products at Factory X and a profit of $120 from the products at Factory Y.
What is the objective function for the scenario above?
P = 600x +12000y
P = 30x + 20y
P = 100x + 1207
P = 40x + 60y

answer
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 16:10, marsewilliams
20 da is equal to a. 2,000 cm. b. 2 m. c. 20,000 cm. d. 20,000 mm
Answers: 1
image
Mathematics, 22.06.2019 02:00, josecano2
What is the area of this parallelogram? 434.28 cm2 263.67 cm2 527.34 cm2 217.14 cm2
Answers: 1
image
Mathematics, 22.06.2019 03:30, baler19
Jack has a rectangular piece of land, the area of which is represented by a1 = 9.5l. his brother has a different rectangular piece of land, the area of which is represented by a2 = l(14 − l). let a represent the area in square meters and l represent the length in meters of the pieces of land. the two equations plotted on a graph meet at a point as shown in the image
Answers: 1
image
Mathematics, 22.06.2019 04:30, donald1255
Write the ratio as a fraction in lowest terms 1 1/2 to 3 1/3
Answers: 1
Do you know the correct answer?
A company makes a product in two different factories. At Factory X it takes 30 hours to produce the...

Questions in other subjects:

Konu
Mathematics, 02.09.2021 14:00