Task: Engineers are digging a 3200-foot-long tunnel at a constant rate. After 5 months, the engineers still need to dig 1700 feet to finish the project. How much time does it take to complete the tunnel from start to finish?

Will the engineers have enough time if the project was started in December 2020 and the deadline to finish the project was in August 2021? Please explain your answer for yes or no.

Hint:
y=mx+b (slope-intercept form)
x=time
y=distance
b=3200
Start & Finish: ??
Total length=3200ft

answer
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 17:40, bigb290
The graph of y = ax^2 + bx + c is a parabola that opens up and has a vertex at (0, 5). what is the solution set of the related equation 0 = ax%2 + bx + c?
Answers: 2
image
Mathematics, 21.06.2019 22:30, magics
Factor the polynomial, if possible. if the polynomial cannot be factored, write prime. 9n^3 + 27n^2 – 25n – 75
Answers: 2
image
Mathematics, 21.06.2019 22:40, liljett
Which of the following functions corresponds to the above sinusoid? a. 10 cos πx - 5 b. -5 sin x - 5 c. -10 cos πx/2 - 0.5 d. 10 sin πx - 5
Answers: 1
image
Mathematics, 21.06.2019 23:50, stricklandashley43
Quick graph the line for y+2=32(x+4) on the coordinate plane. does anyone know the cordinates will mark brainliest.
Answers: 1
Do you know the correct answer?
Task: Engineers are digging a 3200-foot-long tunnel at a constant rate. After 5 months, the enginee...

Questions in other subjects:

Konu
Mathematics, 13.11.2019 05:31