Engineers are digging a 3200-foot-long tunnel at a constant rate. After 5 months, the engineers still need to dig 1700 feet to finish the project. How much time does it take to complete the tunnel from start to finish? Will the engineers have enough time if the project was started in December 2020 and the deadline to finish the project was in August 2021? Please explain your answer for yes or no.

Hint:
y=mx+b (slope-intercept form)
x=time
y=distance
b=3200
Start & Finish: ??
Total length=3200ft
Left over=1700ft after 5 months of digging

help/

answer
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 13:30, 22justinmcminn
Which equation represents a proportional relationship that has a constant of proportionality equal to 1/5
Answers: 1
image
Mathematics, 21.06.2019 21:00, arizmendiivan713
*let m∠cob = 50°30’, m∠aob = 70° and m∠aoc = 20°30’. could point c be in the interior of ∠aob? why?
Answers: 1
image
Mathematics, 21.06.2019 21:30, daii128
The anwser cause i do not understand just plez
Answers: 1
image
Mathematics, 22.06.2019 00:10, saja19
How do i take any fraction and make it into a decimal or percentage?
Answers: 1
Do you know the correct answer?
Engineers are digging a 3200-foot-long tunnel at a constant rate. After 5 months, the engineers stil...

Questions in other subjects:

Konu
Mathematics, 11.09.2021 06:40
Konu
Mathematics, 11.09.2021 06:40