Mathematics, 19.03.2021 14:00, kamryn69

15 men can do a piece of work in 80 days. How long will it take to complete the work, if 5 men are reduced ​

answer
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 17:00, mmassaro19
Amanager recorded the number of bicycles sold by his company each quarter. his projected sales after t years is given by the expression below. which of the following statements best describes the expression? a. the initial sales of 575 bicycles increases at the rate of 4% over 4 quarters. b. the initial sales of 575 bicycles increases at the rate of 18% over 4 years. c. the initial sales of 575 bicycles increases at the rate of 4% over t quarters. d. the initial sales of 575 bicycles increases at the rate of 18% over t years.
Answers: 1
image
Mathematics, 21.06.2019 19:00, abraham1366
Which values of p and q result in an equation with exactly one solution? px-43=-42x+q choose all answers that apply: a) p=-43 and q=-43 b) p=42 and q=43 c) p=43 and q=βˆ’42 d) p=42 and q=42
Answers: 1
image
Mathematics, 21.06.2019 20:00, lexhoangg
Frank owns a $141,000 home, for which he has a 30-year mortgage in the amount of $700 a month. once he has paid off mortgage, how much will he have paid in investment? a. $111,000 b. $109,000 c. $120,000 d. $141,000
Answers: 1
image
Mathematics, 21.06.2019 23:30, sheram2010
Solve the equation: x - 9 = -6 + 5 a. 21 b. 7 c. 14 d. 2
Answers: 2
Do you know the correct answer?
15 men can do a piece of work in 80 days. How long will it take to complete the work, if 5 men are r...