Mathematics, 01.03.2021 19:10, 1060975

The time to complete a project varies inversely with the number of employees. If 3 people can
complete the project in 7 days, how long will it
take 5 people?
O 4.2
O 21
O 11.7
O 2.1

answer
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 18:00, afolmar2006
Write an equation for the function that includes the points (1,4/5) and (2,2/3)
Answers: 1
image
Mathematics, 21.06.2019 20:40, brayann5761
What is the value of the expression i 0 × i 1 × i 2 × i 3 × i 4? 1 –1 i –i
Answers: 2
image
Mathematics, 21.06.2019 21:00, Gabriel134
Gabriel determined that his total cost would be represented by 2.5x + 2y – 2. his sister states that the expression should be x + x + 0.5x + y + y – 2. who is correct? explain.
Answers: 3
image
Mathematics, 22.06.2019 01:00, jtgarner402
The computer that controls a bank's automatic teller machine crashes a mean of 0.6 times per day. what is the probability that, in any seven-day week, the computer will crash less than 5 times? round your answer to four decimal places
Answers: 2
Do you know the correct answer?
The time to complete a project varies inversely with the number of employees. If 3 people can
...

Questions in other subjects:

Konu
Mathematics, 27.03.2020 23:11
Konu
Mathematics, 27.03.2020 23:11
Konu
Mathematics, 27.03.2020 23:12