Mary, John and Sue are working on a large project. From past experience it is estimated that Mary would require 45 days to complete the project, John would require 50 days, and Sue would require 60 days. If they work together, what would be the estimated number of days required to complete this project? I v

answer
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 13:00, enorton
Harry’s soccer team plays 2 nonconference games for every 3 games that they play against conference opponents. if y represents the number of nonconference games and x represents the number of conference games, which equation best models this proportional relationship? a)y=2/3 x b)y=3/2 x c)y = 2x d)y = 6x
Answers: 1
image
Mathematics, 21.06.2019 14:30, helloitschump0vfdz
Organisms that live in the alpine and taiga biomes have developed unique adaptations that aid in their survival. the douglas-fir is a conifer tree that grows in the taiga biome. it has an average height of about 70 feet, and its wood is an important source of lumber.
Answers: 3
image
Mathematics, 21.06.2019 20:30, audrey435
Hi if you want to play a sports related kahoot go to kahoot. it and type in this code: 659344
Answers: 1
image
Mathematics, 21.06.2019 21:00, lizzoone
The? half-life of a radioactive substance is 20 years. if you start with some amount of this? substance, what fraction will remain in 120 ? years
Answers: 1
Do you know the correct answer?
Mary, John and Sue are working on a large project. From past experience it is estimated that Mary wo...

Questions in other subjects:

Konu
Mathematics, 03.02.2020 19:54
Konu
Mathematics, 03.02.2020 19:54
Konu
Mathematics, 03.02.2020 19:54