Mathematics, 23.02.2021 16:10, Deavionaaaaa

8 workers complete a construction of a wall in 6 days. How many workers are needed to complete the construction in 4 days.​

answer
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 16:20, johns2380
Under normal conditions, 1.5 feet of snow will melt into 2 inches of water. during a winter season high in the mountains, 301 feet of snow fell. how many inches of water will there be when the snow melts?
Answers: 1
image
Mathematics, 21.06.2019 18:50, anthonylemus36
Jermaine has t subway tokens. karen has 4 more subway tokens than jermaine. raul has 5 fewer subway tokens than jermaine. which expression represents the ratio of karen's tokens to raul's tokens
Answers: 1
image
Mathematics, 21.06.2019 21:10, halimomohamed
If f(x) = 6x – 4, what is f(x) when x = 8? a2 b16 c44 d52
Answers: 2
image
Mathematics, 21.06.2019 21:30, Jordandenzel
Olive's solar powered scooter travels at a rate of 30 miles per hour. what equation can she use to calculate her distance with relation to the time she traveled? h=hours m=miles 1. h=m+30 2. m=30h 3. m=h+30 4. h=30m
Answers: 2
Do you know the correct answer?
8 workers complete a construction of a wall in 6 days. How many workers are needed to complete the c...

Questions in other subjects: