A house needs to be built and ready to move into by June 1 st . It takes 1 week to clear the land. After that, it takes 4 days to lay the foundation. It takes 2 ½ weeks to put up the framing of the house. The interior of the house will take 9 days to finish. When should the crew start work on the house?

answer
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 16:10, Tori122367
Convert 50 kilogram to pounds. (the conversion factor from kilogram to pound is 2.2046.) a. 52.2 lb. b. 110.2 lb. c. 22.6 lb. d. 47.8 lb.
Answers: 1
image
Mathematics, 21.06.2019 21:00, asiamuhammad6
Rewrite the following quadratic functions in intercept or factored form. show your work. y = 4x^2 - 19x- 5
Answers: 2
image
Mathematics, 21.06.2019 21:10, jaki9
Consider circle o, where and . m∠bpd °. °.
Answers: 3
image
Mathematics, 22.06.2019 05:30, hannahkharel2
Writing proportions. no solving. write all of them ! extraaa points.
Answers: 2
Do you know the correct answer?
A house needs to be built and ready to move into by June 1 st . It takes 1 week to clear the land. A...

Questions in other subjects:

Konu
Arts, 07.01.2021 18:20
Konu
English, 07.01.2021 18:20
Konu
Mathematics, 07.01.2021 18:20