Mathematics, 14.02.2021 01:00, hillarytrinh
A house needs to be built and ready to move into by June 1 st . It takes 1 week to clear the land. After that, it takes 4 days to lay the foundation. It takes 2 ½ weeks to put up the framing of the house. The interior of the house will take 9 days to finish. When should the crew start work on the house?
Answers: 3
Mathematics, 21.06.2019 13:10, markayla61
When eating out, record the total cost of your meal (before tip) and the tip that you left. determine the percent of the cost of the meal that you left as a tip.
Answers: 1
A house needs to be built and ready to move into by June 1 st . It takes 1 week to clear the land. A...