URGENT The time required to complete a job varies inversely as the number of people working. It took 4 hours for 7 electricians to wire a building. How long would it have taken 3 electricians?

A. 1 hour 43 minutes
B. 5 hours 15 minutes
C. 7 hours 30 minutes
D. 9 hours and 20 minutes

answer
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 19:40, NobleWho
Neoli is a nurse who works each day from 8: 00 am to 4: 00 pm at the blood collection centre. she takes 45 minutes for her lunch break. on average, it takes neoli 15 minutes to collect each sample and record the patient's details. on average, how many patients can neoli see each day?
Answers: 3
image
Mathematics, 21.06.2019 23:00, jnsoccerboy7260
The perimeter of a rectangular rug is 24 feet. the length of the rug is 1 2/5 i s width. what is the area of the rug
Answers: 2
image
Mathematics, 21.06.2019 23:40, notearslefttocry14
What is the area of a rectangle with vertices (-8,-2), (-3,-2), (-3,-6), and (-8,-6)? units
Answers: 1
image
Mathematics, 22.06.2019 00:00, christeinberg1
An equation in slope-intersept form the lines that passes thought (-8,1) and is perpindicular to the y=2x-17.
Answers: 1
Do you know the correct answer?
URGENT The time required to complete a job varies inversely as the number of people working. It too...

Questions in other subjects:

Konu
Mathematics, 08.04.2020 20:15
Konu
Mathematics, 08.04.2020 20:15
Konu
Mathematics, 08.04.2020 20:15
Konu
Physics, 08.04.2020 20:15