To complete a task in 16 days a company needs
5 people each working for 6 hours per day.
The company decides to have
8 people each working for 4 hours per day.
Assuming that each person works at the same rate,
how many days will the task take to complete?
Answers: 3
Mathematics, 21.06.2019 17:00, cordovatierra16
Which graph corresponds to the function f(x) = x2 + 4x – 1?
Answers: 1
Mathematics, 21.06.2019 18:00, kyasnead8189
Henry is an avid reader, he devours 90 pages in half an hour how many pages has henry read per minute?
Answers: 1
Mathematics, 21.06.2019 20:00, offensiveneedle
1: 4 if the wew 35 surfboards at the beach how many were short boards?
Answers: 1
Mathematics, 13.04.2021 23:10
Social Studies, 13.04.2021 23:10
English, 13.04.2021 23:10
Mathematics, 13.04.2021 23:10
Mathematics, 13.04.2021 23:10