Nathan and Matt plan to paint a house. If Nathan works alone, it will take 10 days. If Matt works alone, it will take 15 days. How many days will it
take to finish the job if they work together?

answer
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 14:00, zanaplen27
Tiara buys the pizza shown below: a circular pizza is shown. the edge of one slice is marked ab. what does the curve ab represent?
Answers: 1
image
Mathematics, 21.06.2019 14:00, kyusra2008
The graph of a line gets what as the value of the slope gets bigger
Answers: 2
image
Mathematics, 21.06.2019 21:10, koolgurl2003
Starting at home, emily traveled uphill to the hardware store for 606060 minutes at just 666 mph. she then traveled back home along the same path downhill at a speed of 121212 mph. what is her average speed for the entire trip from home to the hardware store and back?
Answers: 1
image
Mathematics, 22.06.2019 00:30, def88
Efficient homemakers ltd. makes canvas wallets and leather wallets as part of a money-making project. for the canvas wallets, they need two yards of canvas and two yards of leather. for the leather wallets, they need four yards of leather and three yards of canvas. their production unit has purchased 44 yards of leather and 40 yards of canvas. let x be the number of leather wallets and y be the number of canvas wallets. draw the graph showing the feasible region to represent the number of the leather and canvas wallets that can be produced.
Answers: 1
Do you know the correct answer?
Nathan and Matt plan to paint a house. If Nathan works alone, it will take 10 days. If Matt works a...

Questions in other subjects:

Konu
Mathematics, 16.01.2021 01:30
Konu
Mathematics, 16.01.2021 01:40