A construction team gives an estimate of three months to repave a large stretch of a very busy road with their core crew of 7 people. The government responds that it is too much of an inconvenience to have this busy road obstructed for three months, so the job must be completed in one month. If the relationship between construction time and crew members is inversely proportional, how many crew members does the construction team need if they are to complete the job in one month

answer
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 15:30, ur4286
The triangles are similar. what is the value of x? show your work.
Answers: 1
image
Mathematics, 21.06.2019 22:00, LilFabeOMM5889
In δabc, m∠acb = 90°, cd ⊥ ab and m∠acd = 45°. find: a find cd, if bc = 3 in
Answers: 1
image
Mathematics, 21.06.2019 23:30, gugu1004
What is the value of x? enter your answer in the box.
Answers: 1
image
Mathematics, 22.06.2019 02:00, amberwilliams22
The table shows values for functions f(x) and g(x) . x f(x)=−4x−3 g(x)=−3x+1+2 −3 9 179 −2 5 53 −1 1 1 0 −3 −1 1 −7 −7 2 −11 −25 3 −15 −79 what is the solution to f(x)=g(x) ? select each correct answer.
Answers: 1
Do you know the correct answer?
A construction team gives an estimate of three months to repave a large stretch of a very busy road...

Questions in other subjects:

Konu
Social Studies, 17.11.2020 03:10
Konu
Mathematics, 17.11.2020 03:10