A and B, working together can finish a piece of work in 6 days, while A alone can do it in 9 days. How much time will B alone take to finish it?

answer
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 17:30, djs1671
Simplify the expression 10/11(22z) + (a+5) -1
Answers: 2
image
Mathematics, 21.06.2019 18:30, sherlock19
What are different types of statistical programs
Answers: 2
image
Mathematics, 21.06.2019 19:00, babygirlmiller
The weight of an object in the water is 7% of its weight out of the water. what is the weight of a 652g object in the water?
Answers: 1
image
Mathematics, 21.06.2019 19:00, mbalderp5bxjo
Billy plotted −3 4 and −1 4 on a number line to determine that −3 4 is smaller than −1 4 is he correct? explain why or why not?
Answers: 3
Do you know the correct answer?
A and B, working together can finish a piece of work in 6 days, while A alone can do it in 9 days. H...

Questions in other subjects: