Ed is managing a construction project. The function y = 0.75x represents the percentage of work done in terms of the number of weeks since the project started. The value 0.75 represents
.

The function representing the percentage of work that remains in terms of the number of weeks since the project started is y =

x.

answer
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 20:00, ale6826
Abcd is a square. what is the measure of angle bac
Answers: 2
image
Mathematics, 21.06.2019 21:00, kfliehman1
Which must be true in order for the relationship △zyv ~ △xwv to be correct? zy ∥ wx ∠z ≅ ∠y and ∠w ≅ ∠x zv ≅ vy and wv ≅ vx ∠z ≅ ∠x and ∠w ≅ ∠y
Answers: 2
image
Mathematics, 22.06.2019 01:20, love0000
Describe how to determine the average rate of change between x = 4 and x = 6 for the function f(x) = 2x^3 + 4. include the average rate of change in your answer.
Answers: 3
image
Mathematics, 22.06.2019 01:50, Aidanme25
If its non of them tell me..valerie took a day-trip. she drove from her house for a while and took a coffee break. after her coffee break, she continued driving. after  2  hours of driving after her coffee break, her distance from her house was  210  miles. her average speed during the whole trip was  60  miles per hour. valerie created the equation  y−210=60(x−2)  to represent this situation, where  xx  represents the time in hours from her coffee break and  yy  represents the distance in miles from her house. which graph correctly represents valerie's distance from her house after her coffee break?
Answers: 1
Do you know the correct answer?
Ed is managing a construction project. The function y = 0.75x represents the percentage of work done...

Questions in other subjects:

Konu
Chemistry, 25.09.2019 16:30