The time to complete a building project is inversely proportional to the number of people working on the job it takes 30 days for 6 workers to complete the job. If they need to complete the job in 20 days, how many workers will they need?

answer
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 13:00, krishawnnn
Shiny white dental insurance costs $258 per year. approximately one-third of insured people need a filling, which averages $110 each. 80% of insured people get a preventive check-up each year, and the average cost of this visit is $95. if you consider shiny whiteโ€™s income and expenses, what is the expected value of each insured customer?
Answers: 1
image
Mathematics, 21.06.2019 16:00, ericavasquez824
The graph shows the distance y, in inches, a pendulum moves to the right (positive displacement) and to the left (negative displacement), for a given number of seconds x. how many seconds are required for the pendulum to move from its resting position and return? enter your answer in the box.
Answers: 2
image
Mathematics, 21.06.2019 17:20, tajonae04
Aboat costs 19200 and decreases in value by 12% per year. how much will it cost in 5 years
Answers: 2
image
Mathematics, 21.06.2019 18:40, s77969
Someone answer this check out the image!
Answers: 1
Do you know the correct answer?
The time to complete a building project is inversely proportional to the number of people working on...

Questions in other subjects:

Konu
Physics, 21.10.2019 22:30
Konu
Biology, 21.10.2019 22:30