Mathematics, 12.12.2020 17:10, bloodyflower2003
A project consists of three tasks: A, B, and C. Task A is known to take five days for sure. Tasks B and C are each dependent on A. B takes five days. C takes seven days with a probability of 0.5 and three days with a probability of 0.5. What is the expected completion time of the project
![answer](/tpl/images/cats/otvet.png)
Answers: 3
Other questions on the subject: Mathematics
![image](/tpl/images/cats/mat.png)
Mathematics, 21.06.2019 20:30, richchillnqueenz1ma
Write an equation of the line that passes through 9,2 and is parallel to the line y=5/3x+9
Answers: 1
![image](/tpl/images/cats/mat.png)
![image](/tpl/images/cats/mat.png)
Mathematics, 22.06.2019 00:30, mercydiaz84
Measure a and b and find their sum. how are the angles related?
Answers: 3
![image](/tpl/images/cats/mat.png)
Mathematics, 22.06.2019 01:30, nikkih1225
Ineed with question three. i don't understand how i'm supposed to achieve 3 marks.
Answers: 2
Do you know the correct answer?
A project consists of three tasks: A, B, and C. Task A is known to take five days for sure. Tasks B...
Questions in other subjects:
![Konu](/tpl/images/cats/ekonomika.png)
![Konu](/tpl/images/cats/fizika.png)
Physics, 07.10.2019 00:00
![Konu](/tpl/images/cats/mkx.png)
![Konu](/tpl/images/cats/informatica.png)
Computers and Technology, 07.10.2019 00:00
![Konu](/tpl/images/cats/obshestvoznanie.png)
Social Studies, 07.10.2019 00:00
![Konu](/tpl/images/cats/en.png)
English, 07.10.2019 00:00
![Konu](/tpl/images/cats/biologiya.png)
Biology, 07.10.2019 00:00
![Konu](/tpl/images/cats/en.png)
English, 07.10.2019 00:00
![Konu](/tpl/images/cats/istoriya.png)