If a worker can do his job in 5 hours, and a student can do the same job in 8 hours, what part of the work is left to finish after two hours of work? NOTE: THEY WORKED TOGETHER ANSWER: FRACTIOn

answer
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 13:50, anasc
(if f(x)=4x^2 and g(x)=x+1, find (f o g)(x)
Answers: 1
image
Mathematics, 21.06.2019 20:30, dbzafgtkiap9wyrl
The number of 8th graders who responded to a poll of 6th grade and 8 th graders was one fourtg of the number of 6th graders whi responded if a total of 100 students responddd to the poll how many of the students responded were 6 th graders
Answers: 1
image
Mathematics, 21.06.2019 21:30, carolyn7938
(03.03 mc) choose the graph below that correctly represents the equation 2x + 4y = 24. (5 points) select one: a. line through the points 0 comma 6 and 12 comma 0 b. line through the points 0 comma negative 6 and 12 comma 0 c. line through the points 0 comma negative 12 and 6 comma 0 d. line through the points 0 comma 12 and 6 comma 0
Answers: 1
image
Mathematics, 21.06.2019 21:30, alex8366
The owner of the plant nursery where you were tells you to fill 350 ml bottles from a 30 l from a fertilizer
Answers: 1
Do you know the correct answer?
If a worker can do his job in 5 hours, and a student can do the same job in 8 hours, what part of th...

Questions in other subjects:

Konu
Mathematics, 18.08.2019 12:50
Konu
Chemistry, 18.08.2019 12:50