An assembly line must create one finished product every 3 minutes. The sum of the task times required to create a product is 700 seconds. What is the theoretical minimum number of workstations for this assembly line

answer
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 14:30, mcouil9369
Which functions are even? check all of the boxes that apply. f(x) = x4 – x? f(x) = x2 – 3x + 2 f(x) = (x - 2) f(x) = x done
Answers: 3
image
Mathematics, 21.06.2019 20:10, snicklegirlp4isqr
The constitution gives congress the power to create federal courts lower than the supreme court higher than the supreme court equal to the supreme court, unaffected by the supreme court.
Answers: 1
image
Mathematics, 21.06.2019 20:30, seth82
What is the length of the segment, endpoints of which are intersections of parabolas y=x2? 11 4 x? 7 4 and y=? 7 8 x2+x+ 31 8 ?
Answers: 2
image
Mathematics, 21.06.2019 21:00, ayoismeisalex
Me! i will mark brainliest! i don't get polynomials and all that other stuff. so this question is really hard. multiply and simplify.(x - 4) (x^2 – 5x – 6)show your
Answers: 2
Do you know the correct answer?
An assembly line must create one finished product every 3 minutes. The sum of the task times require...

Questions in other subjects:

Konu
Mathematics, 12.03.2021 20:50