Mathematics, 18.10.2020 08:01, justinchou814
A construction worker estimates that a kitchen will take 1 Person 200 hours. If 5 people work on the job for 8 hours a day, how many days will it take for them to complete the job?
A) 4
B) 5
C) 6
D) 7
Answers: 2