Mathematics, 06.10.2020 22:01, iris7324

The time required to complete a job varies inversely as the number of people working. It took 22 painters 494 hours to paint a wall. How long
would it have taken 19 people to have done the job?

answer
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 15:00, AJSkullcrusher
This week, conrad will work 1 3/4 times longer than last week. giovanni will work 1 1/3 times longer than last week. sally will work 2/3 the number of hours she worked last week. match each employee's name to the number of hours he or she will work this week
Answers: 1
image
Mathematics, 21.06.2019 18:00, logansgirl3228
Don't know how to find x given these segment lengths
Answers: 1
image
Mathematics, 21.06.2019 20:00, arianaaldaz062002
If the simple annual interest rate on a loan is 6, what is the interest rate in percentage per month?
Answers: 1
image
Mathematics, 21.06.2019 20:30, yfgkeyonna
On a cm grid, point p has coordinates (3,-1) and point q has coordinates (-5,6) calculate the shortest distance between p and q give your answer to 1 decimal place
Answers: 2
Do you know the correct answer?
The time required to complete a job varies inversely as the number of people working. It took 22 pa...

Questions in other subjects: