Mathematics, 19.08.2020 22:01, rsmith4531
If a certain job can be finished by 18 workers in 26 days. How
many
workers are needed to finish job in 12 days?
![answer](/tpl/images/cats/otvet.png)
Answers: 2
Other questions on the subject: Mathematics
![image](/tpl/images/cats/mat.png)
Mathematics, 21.06.2019 12:50, vandarughb2875
Asequence of numbers begins with 12 and progresses geometrically. each number is the previous number divided by 2. which value can be used as the common ratio in an explicit formula that represents the sequence? 1/2 2 6 12
Answers: 3
![image](/tpl/images/cats/mat.png)
![image](/tpl/images/cats/mat.png)
Mathematics, 21.06.2019 18:00, leysirivera23ovez6n
The price of an item has been reduced by 30%. the original price was $30. what is the price of the item now ?
Answers: 1
![image](/tpl/images/cats/mat.png)
Mathematics, 21.06.2019 18:30, joaquin42
Which of the statements about the graph of the function y = 2x are true? check all of the boxes that apply. the domain is all real numbers x because the exponent of 2 can be any real number when the x-values increases by 1 unit, the y-value multiplies by 2. the y-intercept is (0, 1). the graph never goes below the x-axis because powers of 2 are never negative. the range is all real numbers.
Answers: 1
Do you know the correct answer?
If a certain job can be finished by 18 workers in 26 days. How
many
workers are needed to fin...
workers are needed to fin...
Questions in other subjects:
![Konu](/tpl/images/cats/mat.png)
![Konu](/tpl/images/cats/istoriya.png)
History, 04.02.2021 18:00
![Konu](/tpl/images/cats/mat.png)
Mathematics, 04.02.2021 18:00
![Konu](/tpl/images/cats/istoriya.png)
![Konu](/tpl/images/cats/mat.png)
![Konu](/tpl/images/cats/mat.png)
![Konu](/tpl/images/cats/mat.png)
Mathematics, 04.02.2021 18:00
![Konu](/tpl/images/cats/himiya.png)
![Konu](/tpl/images/cats/biologiya.png)