Mathematics, 22.07.2020 06:01, Isaiahtate053

35 workers are employed to complete the construction in 16 days. Before the work starts, he is told to complete the task in 14 days. Assuming that all the workers work at the same rate, how many more workers does he need to employ in order to complete the project.

answer
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 17:30, emiller6462
Use the net as an aid to compute the surface area of the triangular prism. a) 550 m2 b) 614 m2 c) 670 m2 d) 790 m2
Answers: 1
image
Mathematics, 21.06.2019 18:00, tporter00
Write the fraction or mixed number and the decimal shown by the model
Answers: 2
image
Mathematics, 21.06.2019 19:30, shay03littletop5kx2p
Simplify (1/2)4th power a. (1/16) b.(1/8) c.(1/4)
Answers: 2
image
Mathematics, 21.06.2019 19:50, maggie3541
Math it's appreciated. (picture provided)
Answers: 1
Do you know the correct answer?
35 workers are employed to complete the construction in 16 days. Before the work starts, he is told...

Questions in other subjects:

Konu
Mathematics, 03.11.2020 08:10