Mathematics, 08.07.2020 23:01, angelashaw449
(i) You are the cost Engineer for a construction company in charge of building a new
bridge. The construction company will be penalized each day of delay in
construction for bridge. The penalty will be $4500 for the first day and will increase
by $12000 for each following day. Based on its budget, the company can afford to
pay a maximum of $ 155000 toward penalty. By modelling this as an arithmetic
progression, find the maximum number of days by which the completion of work can
be delayed.
Answers: 3
Mathematics, 21.06.2019 16:30, monica1400
The hawaiian alphabet has 12 letters. how many permutations are posible for each number of letters?
Answers: 3
Mathematics, 21.06.2019 18:40, calebhoover03
2people are trying different phones to see which one has the better talk time. chatlong has an average of 18 hours with a standard deviation of 2 hours and talk-a-lot has an average of 20 hours with a standard deviation of 3. the two people who tested their phones both got 20 hours of use on their phones. for the z-scores i got 1 for the chatlong company and 0 for talk-a-lot. what is the percentile for each z-score?
Answers: 1
Mathematics, 21.06.2019 21:50, quennnshyan7276
Which graph depicts the path of a projectile
Answers: 1
(i) You are the cost Engineer for a construction company in charge of building a new
bridge. The co...