(i) You are the cost Engineer for a construction company in charge of building a new bridge. The construction company will be penalized each day of delay in
construction for bridge. The penalty will be $4500 for the first day and will increase
by $12000 for each following day. Based on its budget, the company can afford to
pay a maximum of $ 155000 toward penalty. By modelling this as an arithmetic
progression, find the maximum number of days by which the completion of work can
be delayed.

answer
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 16:30, monica1400
The hawaiian alphabet has 12 letters. how many permutations are posible for each number of letters?
Answers: 3
image
Mathematics, 21.06.2019 18:40, calebhoover03
2people are trying different phones to see which one has the better talk time. chatlong has an average of 18 hours with a standard deviation of 2 hours and talk-a-lot has an average of 20 hours with a standard deviation of 3. the two people who tested their phones both got 20 hours of use on their phones. for the z-scores i got 1 for the chatlong company and 0 for talk-a-lot. what is the percentile for each z-score?
Answers: 1
image
Mathematics, 21.06.2019 21:50, quennnshyan7276
Which graph depicts the path of a projectile
Answers: 1
image
Mathematics, 22.06.2019 04:30, Ryvers
The ordered pair (2,-5.2) is located in quadrant iv
Answers: 1
Do you know the correct answer?
(i) You are the cost Engineer for a construction company in charge of building a new bridge. The co...

Questions in other subjects:

Konu
Mathematics, 24.06.2020 19:01
Konu
English, 24.06.2020 19:01
Konu
Mathematics, 24.06.2020 19:01