Mathematics, 16.10.2019 00:40, Fauxfox
The time to complete a project is inversely proportional to number of people who are doing the project. a certain project can be completed by 5 workers in 24 days. in order to finish the project sooner, the company plans to hire additional workers. how many workers are needed to finish the project in 15 days?
write an inverse variation equation and solve the problem.
Answers: 2
Mathematics, 21.06.2019 20:00, soph10131
M the table below represents a linear function f(x) and the equation represents a function g(x): x f(x)−1 −50 −11 3g(x)g(x) = 2x − 7part a: write a sentence to compare the slope of the two functions and show the steps you used to determine the slope of f(x) and g(x). (6 points)part b: which function has a greater y-intercept? justify your answer. (4 points)
Answers: 3
Mathematics, 21.06.2019 23:00, hjeffrey168
Evaluate each expression. determine if the final simplified form of the expression is positive or negative -42 (-4)2 42
Answers: 2
Mathematics, 22.06.2019 01:40, Conner5459
Astandard deck of cards contains 52 cards. one card is selected from the deck. (a) compute the probability of randomly selecting a diamond or heart. (type an integer or a decimal rounded to three decimal places as needed.) (b) compute the probability of randomly selecting a diamond or heart or club. (type an integer or a decimal rounded to three decimal places as needed.) (c) compute the probability of randomly selecting queen or club. (type an integer or a decimal rounded to three decimal places as needed.)
Answers: 2
The time to complete a project is inversely proportional to number of people who are doing the proje...
Mathematics, 18.03.2021 02:30
Mathematics, 18.03.2021 02:30
English, 18.03.2021 02:30
Mathematics, 18.03.2021 02:30
Mathematics, 18.03.2021 02:30